SDC Environment  Costs i t e r a t i o n - o n e This cost estimate is organized into 44 Work Packages by Phase. Added to these 44 Packages is a contingency figure of 10%. The Contingency will be controlled and distributed by the Sponsor Team on an as-needed basis. | | Phase I: Demolition & Exterior Work | P1-wp5 Demolition Interior West, North and East Wings No work @ Auditorium or 4th floor East Wing | reference: p. 228 | P1-wp7 Abatement Interior West, North and East Wings No work @ Auditorium or 4th floor East Wing | reference: BJ (1/3 due to P1-wp5) | P1-wp10 Cleanup Entire Site Interior and Exterior Debris Removal | reference: p.228 | P1-wp15 Parking Areas Repair of Asphalt Paint Parking Spaces Lighting (West Parking only) Security Fencing (West Parking only) 250 lf of Trellis (10 ft. high - 10 ft.wide) Landscaping (Perimeter of Building and Parking Areas) 155 parking places provided | reference: p. 226 & 228lh | P1-wp20 Access to Streets Cut Curbs Concrete Curbs Asphalt cutting Painting - lane markers | reference: BJ (unusual conditions); p. 229 | P1-wp25 Drainage Repair Existing Storm Sewers New Lines and Grates Grading Asphalt repair | reference: p. 229 | P1-wp30 Building Parameter Waterproofing Excavation Waterproofing Asphalt Repair Landscaping Areas | reference: p. 229 | P1-wp33 Roofing West Wing - New North Wing - New East Wing - Repair Skylight @ Town Square Atrium Note: This work can be spread over Phases I & II with some extra cost for temporary measures and increased risk of damage. | reference: BJ & p. 228 | P1-wp35 Site Repair Curbs Walks Entry Platforms Paving | reference: p. 229 | P1-wp40 Exterior Doors Repair Doors and Bucks Replace Doors and Bucks Hardware Panic Hardware Emergency Lighting w/ battery Repair existing and replace as necessary. | reference: p. 227 | P1-wp45 Exterior Masonry Repair Cleaning Pointup Note: This work can be spread over Phases I & II.. | reference:BJ (15k may be able to come off of this) p.230 | P1-wp50 New West Entry Canopy Glass Walls Platform Paving repair | reference: p. 228 | P1-wp55 New Ornamental Fence & Gates At new North and South Courtyards (Phase II development) | reference: p. 229 | P1-wp60 New Signage At Street - 3 At Parking Lots - 6 At Building Entries - 3 | reference: p. 228 | Phase I Demolition & Exterior Totals | | P1-wp105 Temporary Barriers 6 Total Plywood with locable Doors Graphics | reference: p. 229lh | P1-wp107 Elevator reference: p. 562 Means | P1-wp110 HVAC, Other Mechanical Work Separate Contract Phase I Schedule Must be coordinated with Phase I Work | reference: Jeff Mason | P1-wp110a Electrical Repair and run new electrical as required. Fire A;larm System | reference: p. 230 | P1-wp115 Plumbing as Required Clean and Repair Replace Fixtures (only as necessary) | reference: p. 230 | P1-wp120 Refurbish Hallways and Stairways Clean Paint Patch/replace floor covering | reference: p. | P1-wp125 Prepare 34 Classrooms for Use Floors 1, 2 & 4 (Only) Floor Covering Painting Repair Casework (where possible) Signage Locks (where required) | reference: p. | P1-wp130 Security Office Office Surveillance System Interior halls, building corners, Courtyards, Parking | reference: p. 230 | P1-wp135 Administrative offices Basic Office Shells Glass to Hallways Glass over Partitions Doors, Locks, Signage Floor Covering, Paint Some Lighting (in addition to overheads) Basic Armature System Joseki Level | reference: p. 230 |  View from New Lobby into Admissions Office | | P1-wp140 Town Square Area and Atrium 2 story Atrium under opening Skylight Glass walls Landscaping Seating - benches Kiosks | reference: p. 229lh | P1-wp145 Lobby Floor Finish Seating Area Security Station Adjacent to Security Office | reference: p. 229lh | P1-wp155 Collaborative Work Area Joseki Style 1st Floor Full level Completion and Furnished Stairway to SDC ValueWeb Community Room (above) Open to Hallway | reference: p. 229lh | P1-wp115 SDC ValueWeb Members Community Room NavCenter Style 2nd Floor Full level Completion and Furnished Stairway to Collaborative Work Area (below) Open to Hallway Glass Wall in Hall (North) is Phase II Computing, Web Access & Multimedia | reference: p. 229lh | P1-wp199 Energy Retrofit Separate Contract Phase I Schedule Must be coordinated with Phase I Work | reference: Jeff Mason | | P2-wp10 Library Facilities Full level Completion and Furnished Case Work, soft seating, work areas Printing, High Speed Internet Access | reference: p. 231 | P2-wp20 Student Union Full level Completion and Furnished Case Work, soft seating, work areas Printing, High Speed Internet Access | reference: p. 231 | P2-wp30 Add Features and Amenities to Prior Areas Classrooms, Administration, Town Square, Lobby, Collaborative Workroom, SDC ValueWeb members Community. Trim Built-ins WorkFurniture, TechnologyLighting, Interior Landscaping | reference: p. 231 | P2-wp40 North Entry Canopy Glass Walls Platform Paving repair | reference: p. 228 | P2-wp50 Complete SDC ValueWeb Members Community Room and Adjacent hall Glass Walls at North Wall (Hall - external wall) WorkFurniture Technology Upgrade | reference: p. 231 | P2-wp60 Glass Connection between West and East Wings - 1st Floor Level. Glass Walls Remove existing structure to second level Coordinate with Landscaping (P2wp70) | reference: p. 231lh | P2-wp70 North and South Landscaped Courtyards Remove Paving Patios Planting Remove 2nd floor Bridge between West and East Buildings at North Patio | reference: p. 231lh | P2-wp80 Entry and Stairway to Second Level - North Courtyard, East Wing Remove Paving Remove Existing Entry Ramp to First Floor Level Stairway to Second Floor Level | reference: p. 231lh | P2-wp90 Upgrade HVAC Begins Modernizarion Process | reference: Placeholder | | P3-wp15 Performing Arts Center House: 750 Live and Multimedia Inteface with Student Union | Cost Turn Key: | $3,200,000 | reference: p. 227 | | |
|