SDC Environment

Revised Work Packages
June 2002
A r c h i v e d
as a Record Document

July 26, 2002

 

Anticipating the appraisal and closing, a budget has been established for Phase I-mi (move-in) which is all the work necessary to move-in and for first use. While the original Scope of the four Work Phases remain basically intact, the following describes the actual authorized work to match up with the existing budget. This work is composed of items from Phases I & II (as previously described) in a somewhat different mix than first defined. In the following Chart, the old Work Package numbers that best match up to the authorized work are provided.

Work Packages for move-in
Cost
Item
Description
Old #
70,000
Plmi-wp5
Demo
Removal of all materials for Phases I & II work
PI-wp5
30,000
Plmi-wp7
Abatement
Removal of all dangerous materials
PI-wp7
18,000
Plmi-wp10
Clean Up
Exterior and Interior
PI-wp10
65,000
Plmi-wp1
Security Fencing & Lighting
Security Fencing & Lighting at Parking Area
PI-wp15
20,000
Plmi-wp25
Drainage
Provide drainage at West and North sides and interior Courtyards
Pl-wp25
21,000
Plmi-wp30
Building Parameter Waterproofing
Seal for water penetration into basements & foundations
Pl-wp30
250,000
Plmi-wp33
Roofing
Repair - 10 year Warrantee - Skylight over Atrium
Pl-wp33
11,200
Plmi-wp35
Curbs
Cut & repair Curbs - provide street & parking lot access
Pl-wp35
29,000
Plmi-wp40
Exterior Doors
Repair & replacement as necessary - closures & fire exit signage
Pl-wp40
25,000
Plmi-wp50
New West Entry
Basic Shell & Doors
PI-wp50
20,000
Gates
At North and South Landscape Courts - Complete finish
PI-wp 55
25,000
Plmi-wp60
Signage
Street, Buildings & Parking Areas
Pl-wp60
5,000
Plmi-wp105
Temporary Barriers
Internal to block access to unused areas primarily, access to 4th floor
PI-wp105
80,000
Plmi-wp107
Elevator
Replace - ADA compliant
PI-wp107
95,000
Plmi-wp110
Electrical
All general electrical necessary to move in and to support future work Phases
Pl-wp110
105,500
Plmi-wp115
Plumbing
Necessary for actual use at move-in
PI-wp115
70,000
Plmi-wp120
Hallways & Stairs
Clean, Paint, any necessary new floor covering (minimal) - Signage
PI-wp120
188,000
Plmi-wp125
Classrooms
Paint, Floor Covering, Repair (minimal) - Signage
PI-wp125
39,000
Plmi-wp130
Security
Office and Surveillance System
Pl-wp130
210,000
Plmi-wp135
Administrative offices
Paint, Repair, Floor Covering
Pl-wp135
68,000
Plmi-wp140
Town Square & Atrium
Basic configuration & Skylight (per plan)
Pl-wp140
39,000
Plmi-wp145
Lobby
Basic Level
Pl-wp145
130,000
Plmi-wp160
Library
Fairly high level of development
P2-wp10
81,600
Plmi-wp158
Student Union
Paint, Repair - some development
P2-wp20
64,500
Contingency
 
$1,759,800
Total Phase I mi
Basic functionality and move in accomplished  
 

The budget numbers will be used as the “work to ” design budget to be refined through the pricing/bidding/building process. There is no slack in these numbers. Just under 1.8 million is the minimum figure required for move in (including some key work that can be done after a use permit and move-in). The work that will be accomplished for this figure will be basic: floor covering, paint, electrical and mechanical repair and so on. The work will be done to three levels: A, which is at the the complete “finished” level; B, which is basic work with some further development; and C, which is minimal work necessary for use. A Room Schedule is provided that establishes the finish level for each room in the Phase Imi work period. All of the building areas will be put in use with the exception of the fourth floor and the the Auditorium. Most demolition for future Phase I & II work will be done and the “Town Square" Atrium and skylight is included (finished to a basic level). All future work beyond Phase I mi, however, will add greatly to both functionality and amenity. Phase I mi will give us our basic building - it will be usable and restore a great deal of the quality of the original buildings. Work done beyond this point will have a high value-add factor - both in terms of utility and sense-of-place and in market value.

 

Not covered in this Budget is costs associated with a Sprinkler System which we are going to argue is not necessary given the basic materials, egress and density of use of the facility. Sprinklers will be added and are estimated for each area as it is brought to completion in Phase II, III and IV work. If we lose this argument with the Building Department, we will have a short fall on the order of $300,000 to make up. There is no way to take this out of the other work. A document, showing progressive installation of a sprinkler system, tied to work Phases and time delimited, has been prepared. This work will have to funded by an additional budget.

 

Additional to this Budget is the Energy Refit work PI-wp199.

 

 

Matt Taylor
June 17, 2002
Palo Alto

 

SolutionBox voice of this document:
ENGINEERING • STRATEGY • CONSTRUCTION DOCUMENT

 


posted: June 17, 2002


revised: July 26, 2002
• 20020617.141196.mt • 20020619.761068.mt • 20020726.770911.mt •

Note: this document is complete and archived