|
VCBH
NavCenter
Development
April through September 2002
|
|
|
|
Concept:
April 25, 2002
|
Start:
May 15, 2002
|
 |
 |
|
Install:
June 2, 2002
|
Use:
June 6, 2002
|
Design-Build-Use
Process
|
|
The
Vanderbilt Center for Better Health is employing an
MG Taylor NavCenter to further develop their Rapid
Advance Methodology (RAM) and to deliver Infomatics
technology to their ValueWeb members in the Health
Care Industry. This process is documented elsewhere
(password
protected). This document captures, in real
time, the
history of the FasTrack Design-Build-Use
process as the NavCenter - which will be called the
VCBH Innovation Center - is created and the early
use of the environment as it is brought into full
use.
|
|
The
box in which the NavCenter is being placed
will, in this first phase, have minimal work done
to it. Painting, cleaning and re-stretching the carpet
and upgrading of the hung ceiling tile over the main
large group process area (Radiant Room) is the extent
of it. Two reasons drove this decision: first, the
aggressive schedule of getting the facility ready
for first-use in less than 30 days after the go
decision. And, the desire to evolve the permanent
work-habitat based on the experience of real use -
not a guess of what should be. It is thought
that experience may bring significant changes to the
expected scale and scope of the project. Yet, initially
just installing a RDS level facility for the first
phase was not considered adequate. The key to finding
the happy-medium between a completely built-out architectural
space and a totally portable one was the creation
of an entirely new level of Armature.
This required the rapid-Prototyping, from a first
sketch of an entirely new system of architectural-scale
furniture and successfully installing the first iteration
of the product in less than three weeks. Part of the
functionality of the furniture system had to be the
ability to work well and look done upon
opening, yet, be able to evolve through iterations
of migration from a mostly portable to
a mostly permanent installation.
|
|
This
rapid-Prototyping, FasTracking, iterative approach
to developing a workspace makes a great deal of sense
in todays business environment. The AI Foundation
II series WorkFurniture system is the only one, that
I am aware of, that provides this flexibility while
maintaining the capability and look of being
done at each step along the way.
|
| In
order to meet the schedule, AI manufactured and installed
the Armature System and installed an existing RDS to
provide capability while the WorkFurniture for the layout
below is being produced in the 6 weeks following the
opening. This experience has already provided feedback
that has resulted in some design adjustments. |
|
|

|
|
April
24, 2002 schematic layout of the NavCenter
|
|
|
There
are a number of old AI - and some new ones - that
have been newly reinvented and redone in order to
meet this specific challenge. The Tracery aspect of
the Armature was brought to an entirely new scale
and level of development. In this case the design
employed in the Cambridge project in 1998 was restated
and made considerable lighter and more adaptable.
The Octopus received its first full reworking
since it was first designed in 1996. The Cube-Pod
(a first development from 1990 and 1995 designs) is
built for the first time. The ceiling docking power
poles were recreated using the Gatling post that was
developed for glazing in our Cube Office System in
1999. Several new docking components and rolling bases
were refined to create a new level of dock-ability
and a refined trade-dress.
|
| The
AI Armature System is made up of an number
of components. These are profiled below as they
progressed through the stages of design-development,
installation and first use. |
|
|
Cube-Pod
System -
photos: June 4, 2002
|
 |
| The
Cube-Pod is new and was developed for this project.
We have long wanted a simpler version of the WorkPod
that will plug and play into the other Armature
elements and WorkWalls and roll as a single unit
once assembled. One person can relocated this office
fully loaded. |
|
 |
| This
version of WorkPod is close to the first version I designed
in 1990 which is smaller and less expensive to make
than the more sophisticated 1997 version we prototyped
and installed in several projects in 1997 and 1998.
Both have a role. |
|
 |
| The
original 1990 Pod concept was re-developed in 1995 for
the proposed Vanguard
Center which was not built. |
|
 |
| The
cube elements of the pod are interchangeable and can
be single, double, open glazed of wood filled. The top
ring acts as a lighting armature and connects through
one of the gatling posts to the Tracery to access power,
LAN and A/V to the Pod as required. |
|
 |
| The
top ring floats above the vertical Pod elements
and visually docks to the horizontal Tracery.
Integration and independence is achieved. |
|
 |
| The
Armature System bridges the gap between human scale
and building scale. It provides a variety of elements
than can be used to solve storage, logistical, navigational
and space identity issues. It creates prospect and refuge,
team and large group spaces |
|
|
Tracery
- WorkWall System -
photo: June 5
|
 |
| The
Armature integrates with existing structural elements
providing them an architectural character often lacking
in typical developer commercial building. |
|
|
Monitor
Tree -
photos: June 5
|
 |
| The
Monitor Tree supports three small and one large flat
screens that can display video, data and satellite feeds.
The Tree roles easily and plugs into various ceiling
feeds that provide multimedia and computer input and
output. |
|
 |
| The
Tree can plug into a ceiling (note the birch panels
in place of a ceiling tile) feed or into a Tracery leg.The
entire assemblage rolls and has wire management built-in. |
|
|
First
Use -
photos: June 6
|

 |
| The
Entry to the VCBH Innovation Center is off a 7 story
open Atrium. A glass wall and doors create a transparent
boundary to the space. |
|
 |
| The
Entry creates a simple, inviting space that does not
broadcast what is to come. It brings you in to a comfortable,
intimate and neutral room. |
|
 |
| The
carpet, with a Prairie School motif, anchors the center
of the room and pulls the eye away from the more prosaic
elements of the existing box. This room
within a room device hints at what is to follow. |
|
 |
| A
single wall of strong color, a sign leads to the overly
narrow (existing) opening to a narrow hallway. The design
question was how to use this circumstance
to advantage. |
|
 |
| The
answer: keep the light levels low and introduce Tracery
elements that frame the greater space beyond. Three
carpets create a path within the tunnel which leads
to what now seems like a greatly expanded space. |
|
 |
| The
VCBH Innovation Centers first users enter the
environment for a work
session. This is the diagonal view 180 degrees from
the entry tunnel. The column with the G
Posts is the center of the large area defined by the
Tracery elements (toned on the plan above). |
|
 |
| Conference
participants start to explore the space which has an
abundance of prospect and refuge. |
|
 |
| Books,
displays, toys, tools, work areas, informal areas, open
areas, nooks... Each individual finds a place to comfortable
for them - a place to venture forth from. |
|
 |
| Within
a few minutes the Center was in use with one of its
intended purposes which is large group interaction and
collaboration. |
|
 |
|
The
VCBH ValueWeb dialog begins...
Prospect
and refuge combine to form a creative PLACE.
Elements mostly lacking in the so-called modern
workplace.
|
|
Picture
Gallery of the building and first use of the VCBH
by Alicia Bramlett
|
|
| The
VCBH Innovation (NavCenter) will support a wide variety
of research and client support work that will require
detailed project management. An area dedicated for that
function was installed by the AI KreW on the 22nd and
23rd. This consists of a U shaped area with
a large adjustable Team Table in the center. The center
24 foot WorkWall facilitates strategy AndMaps and the
side WorkWalls Time and Task Maps. On the backside of
these walls are storage bins for support materials and
project materials. The side 12 foot WorkWalls swing
out to expose an additional 24 linear feet of work surface
on each side. When open they enclose the
area to priovde more intimacy. In total, there is 876
square feet of working/display surface provided. Enough
to develop and show a project in some detail. |
|
|
|
| The
Tracery fascia board brings scale to the space and provides
structure for 12 volt lighting. |
|
|
|
| The
Work Team table is composed of a center piece that functions
independently or accommodates a number of large and
small AI tables. This way, a number of different subgroups
can work while still having easy access to the energy
and information of the larger team. |
|
|
|
| Looking
into the Project Management Area from the KnowledgeWorker
Support Team Area. |
|
|
|
| The
ceiling lights will be recycled, over time, to full
spectrum lighting; this along with the 12 volt lighting
(now being designed) will improve the color signature
of the space. It can be seen from these photos that
this is necessary - particularly this far from the windows. |
|
|
|
| On
the right hand side: storage bins, WorkFurniture Storage
and Exit to the Stairwell. |
|
|
|
| On
the left hand side: storage bins and Exit to the internal
hallway. Both these side spaces are different in dimension
and in the location of their exits. |
|
|
|
| Looking
back from the Project Management Area at the Entry and
Pod. The KnowledgeWorker Octopus
Workstation will be connected to the wall, on the
right hand side, past the corner completing the transition
between the open areas and the Project Management space. |
|
|
|
Spaces
should have continuity, yes; They should be flexible
and able to multitask, yes; AND, each niche
must support, indicate and reflect the kind
of work that is to take place within it. It must,
to be effective, provide the appropriate tooling and
ambiance for that work. It has to be specific
- not generic. Those who work here will remember
their experience and work in context of place - The
architecture you see here goes beyond utility. It
it not, however, decoration. It is ART
and as such has a practical role in the workplace.
Everything SPEAKS and NavCenters are one of
the few places where this is recognized and used an
an active principle of the design and the management
of the environment - and the work that takes place
within it.
|
|
The
VCBH Innovation Center (NavCenter) has several major
functions that require a unique setting: research,
knowledge-management and archiving, collaborative
design, project management, venture management and
promotion, rapid-prototyping, education delivery and
learning, multimedia production to name some. These
functions require that large group, teamwork and individual
work can be done discretely (and in parallel in various
parts of the Center) and with everyone being able
to shift mode at a moments requirement. In addition,
technology has to seamlessly support all of these
work-modes and employ the 10
Step Process making the entire environment a knowledge-factory.
|
 |
| 1982
MG Taylor technology
vision. Teams working in multiple modes their
work augmented by multimedia - all interactions
documented, shared properly and archived. |
|
|
The
following photos, of the installation process, show
how quickly and easily the system goes in and the
transforming effect that it has on an otherwise prosaic
space. A box of no particular distinction has been
made to fit a specific function by the employment
of modular furniture with a dash of local adaptation.
We use wood because of its many qualities: strength,
flexibility, durability, warmth, reparability. It
also allows us a lean mix between manufacturing
and custom response in a way that is both sustainable
and affordable.
|
| This
makes a System of manufacturing but not
in the usual sense of common usage. SYSTEM in
this context refers to the entire organizational
effort and design and manufacturing and
operations and client participation (and using)
in the making of the total environment over time. |
|
| This
Tracery piece, which matches other pieces previously
installed in the space, is being attached to the hung
ceiling. |
|
|
| The
Gattling Posts and their column ties are installed.
This echoes the grammar used in the group process
spaces. |
|
|
| By
keeping the pieces separate from the column, yet integrated,
the impact of original construction irregularities
is greatly minimized. Product is made to precise dimensions
- error taken out in the gaps. |
|
|
| In
go the arches and the storage units which are placed
on a leveling base and remain free of any other building
contact. |
|
|
| WorkWalls
are started on the inside of the storage units. The
back of the wall making the back of the unit. Half-section
G Posts are placed on the far wall to
receive arches. |
|
|
| Installation
of the hanger for the wall mounted WorkWalls. |
|
|
| The
Tracery piece and Storage unit/WorkWalls are complete. |
|
|
| Second
level Tracery installation starts. The space takes
shape. |
|
|
| The
long WorkWall is complete and the fascia is started. |
|
|
| G
Posts and wire chases complete the work. |
|
|
|
|
The
AI Shop went from final design to complete installation
of this phase of the project in about 10 days. The
same workers who did the manufacturing did the installation.
Immediate feedback without need for management intervention.
The Shop is also deeply involved in the design process
and develops final CAD drawings for all products.
In total, idea to design to engineering to building
and installing is a seamless process. And a fun one.
|
| The
Project Management space now fits with the group process
areas installed a couple of weeks before. The entire
environment is just beginning the process of settling
in as the owners start the process of making it their
own. Already the environment is starting to evolve as
the USE process begins. Living environments can
be designed - and they can be constructed. They come
to life - when the do come to life - because of how
they are employed.
The architect-builder can make the potential. Only those
living in the space breath life into it. |
|
|
|
Once
a grammar for a project has been determined, there
then exists a reservoir of patterns that
can be applied to localized design and fitness
problems. This informs and delimits the design decisions
that are made along the way from inception to completion.
This simplifies the design process greatly. Unique
and well integrated environments are conceived and
built in less time than most organizations can do
the design and engineering. This design smarts
is embedded in the entire organization and every person
in it. Besides providing organizational efficiency
this way of working makes job enhancement.
It is just more fun to work where thinking is required
and you can make what you think about become real
in concrete FORM.
|
|
This way of working and the FasTracking, design-build
rapid-Prototyping process is the process that
the NavCenters are created to facilitate in the broader
reread of the users work. The fact that they
are built by the same process they promote is not
lost on the subsequent users. It is a proof of concept
thing. Would you ask an organization to bet their
future on a process that failed to work when building
the environment in which the work was to be done?
|
| NavCenters
are places of integrity. They have to be in order to
do their work. Every aspect of their creation and use
must reflect this principle. They are environments where
certain attributes are demanded of the user. They must
be invention, innovation, quality, playfulness,
study, dialog, production, economy. They must
be the result of collaboration, Design/Build/Use,
rapid prototyping, FastTracking. An environment is
how it is designed, built and used. |
|
|
The
final install of various sections of the layout started
the weekends of July 27th and August 3rd. The final
work will be completed August 10 in anticipation of
the VCBH Open House on August 12th. In total, this
work includes the installation of the Octopus Workstation
in the KnowledgeWorker Area, the Star Wall for the
Research Team areas, The rolling/folding Anaconda
Wall, Rolling Book Case/Workstation Units and integrated
12 volt lighting fixtures.
|
| The
Octopus is a horizontal rolling Armature that
creates an easily adjustable set of work niches
where Wings and other Workstations can dock. Power,
LAN, phone, video feeds are provided from one
source - in this case the wall. |
|
|
| The
Octopus creates a space within a space; it defines
a vertical and Horizontal domain - defined yet
open. |
|
|
| Adjustable
bookends sit on the top rail allowing resource
materials to be close to the various docking
work station wings. |
|
|
| Octopus
wall detail - the feeds come in here - looking
toward the Project Management area. Foreground,
middle ground, background on every axis. |
|
|
Since
the June 6th opening day, The VCBH Innovation Center
has been setting up systems, holding Discovery and
Sponsor Sessions and training. The first full up use
of total Center capability will be in September when
two DesignShops will be done - one for an internal
Vanderbilt project and one for an external Vanderbilt
client. Two back-to-back DesignShops
make a robust test of any environment and its support
systems. The VCBH will have gone from an idea to a
fully capable system in four months. The first cycle
(by no means the last) of Design/Build/Use will be
complete.
|
|
The
complete transfer process of the Taylor methods and
the integration - and reinvention - of these methods
into the VCBC RAM system of work
will take about a year from this point forward. This
transfer is accomplished by a combined team of VCBH
and MGT KnowledgeWorkers learning and working together.
Robust capability exists from the beginning. This
starting capability is transformed through experience
and use. It migrates from the general (the sum of
all past experiences) to the specific (what is required
for full efficacy at this installation).
Over the year, the MG Taylor KreW shrinks and the
VCBH KreW grows. NavCenters are created first by cloning
and then matured by transformation. The process
of making a NavCenter is the installing of a dynamic
OS
that then recreates itself. It should be clear, then,
why this has to be done quickly.
|
| A
touch sensitive light switch for the 12 volt lighting
at the entry tunnel. |
|
|
| Brian
Ross assembling the first 12 volt light fixture
for the Entry tunnel. |
|
|
| Three
of the lights in place. Also note the newly installed
flip-up serving tables for refreshments and materials.
When the lights are lifted off their track, they
turn off and on again when placed in a new location.
A simple solution that makes track lightin
truly adjustable - at last! |
|
|
| Copper,
wood, glass - light and design - combine to make
an easy to move custom fixture that reflects and
reinforces the architectural theme of the Center. |
|
|
|
This
lighting is the result of a collaboration
between PipeDreams and the MG Taylor AI production
Krew. It builds off the earlier work done on the Joseki
project. We have wanted - for years - to more
fully integrate lighting with our WorkFurniture and
Armature systems. Joseki, Vanderbilt and the SDC projects
are our first major inroads to this ambition. The
PipeDreams idea is to engineer a basic infrastructure
(out of common off-the-shelf components and copper
water piping that anyone can install) and to encourage
the design of a wide variety of hand-crafted fixtures
that have artistic as well as architectural character.
All this promises a far better product at a fraction
of the price now provided by the lighting industry
which tends to be expensive, unimaginative and narrow
in the range of their solution sets.
|
| The
WorkFurniture installed at Vanderbilt exhibited many
new designs. In addition several old standards
were refined. The round table received a new method
of attaching the top to the legs (iteration 7 or 8,
I think) and also came with a design developed a couple
of years ago but just now built for distribution. In
this version, the legs stay attached to one another
and fold for storing. They attach to the top by a screwed
mechanism that also doubles as a wire hole to the top.
The legs are pulled tight to the top making
leveling much easier. |
 |
| How
many tables look this good underneath? Well, got
that one done
at least! I first designed this table in the early
80s. Langdon Morris, Bill Blackburn, Brian Ross
and Paul Lyon all made improvements over the years.
This is the most refined version. The idea of
the table is to be easily set
up, taken down and stored. |
|
|
|
|
The
12 volt lighting system installation was mostly completed
By the 10th of August AI work session. A few refinements
are to follow. The lights make the Armature System
seem tree-like and combine ornament and
utility making a semitransparent layer between ceiling
and human-occupied space. This enhances the sense
of shelter of the space and obscures the more mundane
aspects of the preexisting ceiling system.
It will be possible, now that these lights are installed,
to re-switch the existing ceiling lighting so that
these lights can be on full, on 75%, on 50% or off.
This will provide variable lighting levels suitable
for different activities and moods at different areas
of the space at different times. The existing fluorescent
bulbs will also be changed out to full spectrum tubes
over time. This, with the 12 volt lighting and a greater
reliance on natural window lighting, greatly modifies
the light signature of the space. Modern workplaces
are usually over lit and fail to differentiate between
ambient, general, task, highlight and effect lighting.
This oversight typically creates a washed-out space
that offer little variety and visual relief. Both
prospect and refuge are sacrificed.
|
| This
installation of this lighting system is the second iteration,
in as many months, of four
projects. |
|
|
|
The
VCBH had its open house and reception on the evening
of August 12th. This was the first opportunity for
the wider Vanderbilt community to see the space.
bill_stead
|
| Bill
Stead welcoming visitors to the VCBH Innovation
Center. Bill is a leading proponent and innovator
of Biomedical Informatics and driving force behind
the VCBH RAM process. |
|
|
| Cyril
Stewart (right) is an architect and Dir. Medical
Center Facility Inventory & Planning Space
& Facilities Planning at Vanderbilt University. |
|
|
|
|
In
September, The VCBC Innovations Center did two back-to-back
DesignShop events. This was the first full scale test
of the facility as a system.
|
| This
experience completes the the first phase of USE.
Essentially, there were no surprises. Everything performed
as expected. |
|
|
|
The
VCBH Design/Build/Use process demonstrates that several
methods and approaches often thought to be inimical
can in fact be integrated into an iterative and seamless
way of building.
|
|
Christopher
Alexander has pointed out the architecture is
often better accomplished when buildings evolve slowly
over time. I agree with this. Steward
Brand wrote the seminal book on the subject How
Buildings Learn. In seemingly juxtaposition to
these viewpoints is the reality that modern finance
and business demands requires very rapid and complete
building processes. This approach has been responsible
for a great deal of the environmental atrocities now
spread around the planet. My contention, however,
is that this is the result of a misuse of rapid design-build
methods and is not the inevitable result of the technique.
I have been employing extreme time compression in
building for years without sacrifice to design or
sensibility.
|
|
The
resolution of this is in the integration of the approaches
and by imposing a rigorous iterative Design/Build/Use
process and by employing a true ValueWeb in high frequency
collaboration.
|
|
We
did evolve the design - and changed it - throughout
this project. The environment will continue to develop
for some time to come. It takes a year of extensive
use of an environment of this kind to even learn its
many possibilities. Each insight will suggest changes
and additions that further augment the environment.
Many contributed to the design and its execution.
Their contribution comes from their own unique perspective,
the actual work they do - and how they do it. All
aspects of USE feedback to the ongoing development
of the work.
|
|
A
flexible approach to building flexible environments
requires a great deal more disciple than conventional
methods. Conventional methods are control focused
and seek to limit variety. This is why they are so
often dull and prosaic. To achieve an organic response
means to increase variety; it means to release control.
It requires the discipline of systematic EMERGENCE.
|
| This
project was started along with two
others. All three projects are different in scale
and location. Each, however, involves a community -
a ValueWeb. Each explores a different aspect of making
a new way of building. Each is an unique expression
and each draws from not only my 46 years of experience
but from roots that go far further back in time. |
|
|
Matt
Taylor
May 21, 2002
Palo Alto

SolutionBox
voice of this document:
USE LOGISTICS PRODUCTION MANAGEMENT
|
posted:
May 21, 2002
revised:
September 20, 2002
20020521.027356.mt 20020622.199021.mt
• 20020608.111199.mt 20020609.876519.mt
• 20020625.659982.mt
20040804.209981.mt •
20020813.777661.mt
20020818.222201.mt •
200209.123409.mt •
note:
this document is about 99% finished
Copyright©
Matt Taylor 2002
Aspects
of the work shown and described are Patented and Pending
by iterations
|
|
|