Anticipating
the appraisal and closing, a budget has been established
for Phase I-mi (move-in) which is all the work necessary
to move-in and for first use. While the original Scope
of the four Work Phases remain basically intact, the
following describes the actual authorized work
to match up with the existing budget. This work is
composed of items from Phases I & II (as previously
described) in a somewhat different mix than first
defined. In the following Chart, the old Work Package
numbers that best match up to the authorized work
are provided.
|
|
Work
Packages for move-in
|
|
Cost
|
Item
|
Description
|
Old
#
|
|
70,000
|
Plmi-wp5
Demo
|
Removal
of all materials for Phases I & II work |
PI-wp5
|
|
30,000
|
Plmi-wp7
Abatement
|
Removal
of all dangerous materials |
PI-wp7
|
|
18,000
|
Plmi-wp10
Clean Up
|
Exterior
and Interior |
PI-wp10
|
|
65,000
|
Plmi-wp1
Security Fencing & Lighting
|
Security
Fencing & Lighting at Parking Area |
PI-wp15
|
|
20,000
|
Plmi-wp25
Drainage
|
Provide
drainage at West and North sides and interior
Courtyards |
Pl-wp25
|
|
21,000
|
Plmi-wp30
Building Parameter Waterproofing
|
Seal
for water penetration into basements & foundations |
Pl-wp30
|
|
250,000
|
Plmi-wp33
Roofing
|
Repair
- 10 year Warrantee - Skylight over Atrium |
Pl-wp33
|
|
11,200
|
Plmi-wp35
Curbs
|
Cut
& repair Curbs - provide street & parking
lot access |
Pl-wp35
|
|
29,000
|
Plmi-wp40
Exterior Doors
|
Repair
& replacement as necessary - closures &
fire exit signage |
Pl-wp40
|
|
25,000
|
Plmi-wp50
New West Entry
|
Basic
Shell & Doors |
PI-wp50
|
|
20,000
|
Gates
|
At
North and South Landscape Courts - Complete finish
|
PI-wp
55
|
|
25,000
|
Plmi-wp60
Signage
|
Street,
Buildings & Parking Areas |
Pl-wp60
|
|
5,000
|
Plmi-wp105
Temporary Barriers
|
Internal
to block access to unused areas primarily, access
to 4th floor |
PI-wp105
|
|
80,000
|
Plmi-wp107
Elevator
|
Replace
- ADA compliant |
PI-wp107
|
|
95,000
|
Plmi-wp110
Electrical
|
All
general electrical necessary to move in and to
support future work Phases |
Pl-wp110
|
|
105,500
|
Plmi-wp115
Plumbing
|
Necessary
for actual use at move-in |
PI-wp115
|
|
70,000
|
Plmi-wp120
Hallways & Stairs
|
Clean,
Paint, any necessary new floor covering (minimal)
- Signage |
PI-wp120
|
|
188,000
|
Plmi-wp125
Classrooms
|
Paint,
Floor Covering, Repair (minimal) - Signage |
PI-wp125
|
|
39,000
|
Plmi-wp130
Security
|
Office
and Surveillance System |
Pl-wp130
|
|
210,000
|
Plmi-wp135
Administrative offices
|
Paint,
Repair, Floor Covering |
Pl-wp135
|
|
68,000
|
Plmi-wp140
Town Square & Atrium
|
Basic
configuration & Skylight (per plan) |
Pl-wp140
|
|
39,000
|
Plmi-wp145
Lobby
|
Basic
Level |
Pl-wp145
|
|
130,000
|
Plmi-wp160
Library
|
Fairly
high level of development
|
P2-wp10
|
|
81,600
|
Plmi-wp158
Student Union
|
Paint,
Repair - some development |
P2-wp20
|
|
64,500
|
Contingency
|
|
|
|
$1,759,800
|
Total
Phase I mi
|
Basic
functionality and move in accomplished |
|
|
|
The
budget numbers will be used as the work to
design budget to be refined through the pricing/bidding/building
process. There is no slack in these numbers. Just
under 1.8 million is the minimum figure required for
move in (including some key work that can be done
after a use permit and move-in). The work that will
be accomplished for this figure will be basic: floor
covering, paint, electrical and mechanical repair
and so on. The work will be done to three levels:
A, which is at the the complete finished
level; B, which is basic work with some further
development; and C, which is minimal work necessary
for use. A Room
Schedule is provided that establishes the finish
level for each room in the Phase Imi work period.
All of the building areas will be put in use with
the exception of the fourth floor and the the Auditorium.
Most demolition for future Phase I & II work will
be done and the Town Square" Atrium and
skylight is included (finished to a basic level).
All future work beyond Phase I mi, however, will add
greatly to both functionality and amenity. Phase I
mi will give us our basic building - it will be usable
and restore a great deal of the quality of the original
buildings. Work done beyond this point will have a
high value-add factor - both in terms of utility and
sense-of-place and in market value.
|
|
Not
covered in this Budget is costs associated with a
Sprinkler System which we are going to argue is not
necessary given the basic materials, egress and density
of use of the facility. Sprinklers will be added and
are estimated for each area as it is brought to completion
in Phase II, III and IV work. If we lose this argument
with the Building Department, we will have a short
fall on the order of $300,000 to make up. There is
no way to take this out of the other work. A
document, showing progressive installation of
a sprinkler system, tied to work Phases and time delimited,
has been prepared. This work will have to funded by
an additional budget.
|
| Additional
to this Budget is the Energy Refit work PI-wp199. |
|
|
Matt
Taylor
June 17, 2002
Palo Alto

SolutionBox
voice of this document:
ENGINEERING STRATEGY CONSTRUCTION
DOCUMENT
|
posted:
June 17, 2002
revised: July 26, 2002
20020617.141196.mt
20020619.761068.mt 20020726.770911.mt